Metro work gathers pace

Praveen Dhaneshkar, Bangalore:

While the Central Business District could look forward to Reach-1 (Baiyappanahalli to Cricket Stadium) going operational in December this year, residents and commercial establishments in Reach 2, 3 and 4 will have to wait for more than two more years for Namma Metro on Phase 1 to go fully operational.


According to B L Yashawanth Chavan, spokesperson for Bangalore Metro Rail Corporation Limited (BMRCL), construction work on the above three reaches is progressing as per deadlines and would gather pace, once the underground stretch begins by the end of this month or early March at Dr B R Ambedkar Veedhi.

“Demolition of structures are almost complete on Reach 2, while 95 demolition works are over at Reach 3. Road widening work to facilitate movement of vehicles in Reach 2 between Magadi Road and Mysore Road terminal is nearing completion,” he said.
Chavan added that they were also in the process of completion of utilities shifting (Bescom cables and BWSSB sanitary pipes) in coordination with civic departments on Reach 3 from Malleshwaram to Rajajinagar station.

Foundation work at all stations in these three Reaches under the 42.3 km Phase 1 is also progressing and would be completed by September 2012. Construction of piers (concrete pillars) and launching of girder segments (concrete bridges) at R V Road and Nanda Road in Basavanagudi and Jayanagar will also be completed within the next two years, he added.
DH News Service

*Reach 2 (Magadi Road to Mysore Road Terminal):
Toll Gate, Hosahalli, Vijayanagar, Mysore Road, Deepanjali Nagar and Mysore Road terminal
*Reach 3 (Swastik to
Yeshwantpur): Malleswaram, M K K Road, Rajajinagar, Mahalakshmipura, Government Soap Factory and Yeshwantpur
*Reach 4 (K R Market to R V Road): South End, Lalbagh,
K R Road, R V Road and Jayanagar

Land and property
acquisition for project
*Number of private
properties proposed for
possession for project: 1107
*Possession taken: 604
*Demolished: 556

The route taken
*East West corridor: Baiyappanahalli terminal to Mysore Road terminal: 17.90 kms
*North South corridor: Hesaraghatta cross to R V Road: 23.87 km

Go to Top

Movie Guide
A Scene from the movie AK 56

AK56 is a Kannada language film by action film director Om Prakash Rao. It is Siddanth's second[...]

Related News
Photo Gallery
Gautam Gambhir of India plays the ball during their ODI cricket match against Australia

Gautam Gambhir of India plays the ball during their ODI cricket match against Australia

India's Virat Kohli bats against Australia during their One Day International series cricket match

India's Virat Kohli bats against Australia during their One Day International series cricket match

A flower vendor busy at his whole sale shop to sell roses in Koyambedu

A flower vendor busy at his whole sale shop to sell roses in Koyambedu

Models on the ramp during a fashion show

Models on the ramp during a fashion show

Vintage cars participate in the 46th Statesman Vintage & Classic Car Rally in New Delhi

Vintage cars participate in the 46th Statesman Vintage & Classic Car Rally in New Delhi

Army Chief General VK Singh flags off the 46th Statesman Vintage & Classic car rally in New Delhi

Army Chief General VK Singh flags off the 46th Statesman Vintage & Classic car rally in New Delhi

Union Minister of Commerce, Industry & Textiles, Anand Sharma in a Press meet

Union Minister of Commerce, Industry & Textiles, Anand Sharma in a Press meet

Congress General Secretary Rahul Gandhi and Priyanka Gandhi Vadra during election campaign

Congress General Secretary Rahul Gandhi and Priyanka Gandhi Vadra during election campaign

Queen of Pop music at her best during the Billboard Awards at the MGM Grand in Las Vegas

Queen of Pop music at her best during the Billboard Awards at the MGM Grand in Las Vegas

Sir Richard Branson arrives at the Beverly Hilton Hotel

Sir Richard Branson arrives at the Beverly Hilton Hotel