Karnataka Dy CM D K Shivakumar seeks faster green nod for Kalasa-Banduri projectIn a representation made to the Union Minister, Shivakumar, who is also in charge of the Irrigation Ministry, argued that the project remains critical for the state's water needs.
Ajith Athrady
Last Updated IST
<div class="paragraphs"><p>Karnataka's Deputy Chief Minister D K Shivakumar with Union Forest Minister&nbsp;Bhupender Yadav.</p></div>

Karnataka's Deputy Chief Minister D K Shivakumar with Union Forest Minister Bhupender Yadav.

Credit: Special Arrangement 

New Delhi: Karnataka's Deputy Chief Minister and and Irrigation Minister D K Shivakumar on Wednesday met Union Minister for Environment and Forest Bhupender Yadav and requested him to expedite environmental clearance for the Kalasa-Banduri irrigation project in Karnataka here.

ADVERTISEMENT

The DCM appealed the Centre to expedite the forest and wildlife clearance for Kalasa Nala diversion scheme and forest clearance for Banduri Nala Diversion scheme.

“Kalasa-Banduri is a critical project for the people of Karnataka. Despite adherence to all statutory and procedural requirements, Karnataka’s proposal continues to face delays. It is imperative to resolve this at the earliest to avoid further impact on this vital project,” the DCM said in the letter.

The 80th meeting of the Standing Committee of the National Board for Wildlife, held in October this year, had deferred the Karnataka’s proposal to use 10.88 hectares of forest land for the Kalasa project in Western Ghats. The Board had directed Karnataka to submit a written representation addressing legal issues raised in the meeting.

The National Board for Wildlife had rejected Karnataka’s proposal citing legal disputes between Goa, Karnataka and Maharashtra related to Mahadayi Water Dispute Tribunal’s award, which was pending before the Supreme Court.

However, Karnataka had contested the decision of the National Board for Wildlife stating that the Supreme Court does not restrain Karnataka from proceeding with the project. Karnataka had also stated that the 10.68 hectares of forest land needed for the project was not part of the wild life sanctuary but was part of the tiger corridor. Karnataka had also listed out the benefits of the project stating that it would provide a water body for the wildlife in the area.

“Karnataka has reduced the forest land requirement for the Kalasa project from the original 258 hectares, which was approved in-principle in 2003, to just 26.92. We also reduced the forest land requirement for Bandura project from 243 hectares to 28.44 hectares. This reflects our commitment to conservation. It is in the state’s interest that the Union Government has to ensure that this project is cleared without any further delay,” the letter urged.

Separately, Shivakumar also met Union Food and Consumer Affairs Minister Pralhad Joshi and requested him to extend help to get approval from Forest Ministry about the project. The DCM also asked Joshi to use his good office to get approval for Mekedatu project, final notification of the Upper Krishna project, sanction money for Upper Bhadra project.