Press Esc to close
Saturday 10 December 2016
News updated at 12:54 AM IST
Weather
Max: 28.9°C
Min : 18.4°C
In Bengaluru
Partially cloudy

Delay in canal repair works worries ryots

Basavaraj Havaldar ,Mandya, Feb 1, 2013, DHNS:

Three tenders cancelled for the work sought by same contractor

The delay in upgradation works of Visvesvaraya canal of Krishnarajasagar reservoir and other channels of Mandya district that was launched two months ago has caused concern among the farming fraternity as the tender process is still pending.

Raitha Sangha leaders are worried over the chain reaction that would affect the farmers.
The delay in works is delay in completion. Until the works are complete it is not possible to release water to the channels which will surely take a beating on the agricultural activities.

Chief minister Jagadish Shettar had launched the upgradation programme in Mandya on November 23. He had disclosed that the tender process are in the final stages and works would begin in the first week of January. Release of water into the canals were stopped on December 31 to facilitate repair works.

Even after a month, not even the tender process is complete, the farmers claimed. The canals of KRS dam are in a poor condition and the tail-end farmers are not getting water.

Hence, demand for upgradation of canals are in the cards since many years. Finally, the state government had divided the restoration works of the canals in the region into five packages at a cost of Rs 330 crore. There are 1,500 km long canals in the dam limits and after inspection it has been decided to upgrade more than 560 km long canals on priority basis.

Initially it was planned to invite tenders in 11 packages. Later, it was reduced to five citing the delay in works may benefit farmers only after the pre-monsoon season. But
even after these exercises, there are no signs of beginning the work.

Cauvery Neeravari Nigam had invited tenders in five packages and three tenders were cancelled as it was submitted by the same person. Now, tenders are being invited for the second time, clarifies the officials. The time given to the contractors will be six months to complete their work and accordingly the works have to be finished by August second week. The question haunting every body is whether this is possible? The delay has caused anxiety among the farmers as if the upgradation is not completed within the scheduled time it means no water for crops. District-in-charge minister C P Yogeeshwar said he had directed the officials concerned to finish the works on war footing.
Ryots have also submitted a memorandum in this regard.

 

Go to Top

Photo Gallery
Artistes perform during the International Gita Mahotsav-2016 in Kurukshetra...

Artistes perform during the International Gita Mahotsav-2016 in Kurukshetra...

Tibetan spiritual leader, the Dalai Lama at the inauguration of a four-day seminar on legacy...

Tibetan spiritual leader, the Dalai Lama at the inauguration of a four-day seminar on legacy...

Two rats gather in a shrub at the Saint Jacques Tower park, in the center of Paris...

Two rats gather in a shrub at the Saint Jacques Tower park, in the center of Paris...

A wrecked bus after meeting with an accident on the Delhi-Agra National highway due to fog...

A wrecked bus after meeting with an accident on the Delhi-Agra National highway due to fog...

Smoke rises from the house where two Lashkir-e-Toiba (LeT) militants were hiding...

Smoke rises from the house where two Lashkir-e-Toiba (LeT) militants were hiding...

Huge cash seized by the Income Tax department after it conducted searches in Chennai...

Huge cash seized by the Income Tax department after it conducted searches in Chennai...

The carcass of elephant Sidda being shifted in a lorry for the burial at the Manchanbele dam...

The carcass of elephant Sidda being shifted in a lorry for the burial at the Manchanbele dam...

A heater is placed in the enclosure of a tiger to keep big cat warm during cold day at Sanjay...

A heater is placed in the enclosure of a tiger to keep big cat warm during cold day at Sanjay...

Umpire Paul Reiffel is helped by support staff after he was hit by ball during fourth test...

Umpire Paul Reiffel is helped by support staff after he was hit by ball during fourth test...

TMC members during a protest to observe a 'Black Day' against demonetization...

TMC members during a protest to observe a 'Black Day' against demonetization...

Like us on Facebook

Copyright 2014, The Printers (Mysore) Private Ltd., 75, M.G Road, Post Box 5331, Bengaluru - 560001
Tel: +91 (80) 25880000 Fax No. +91 (80) 25880523