Metro Reach-1 likely to miss deadline

Last updated: 09 September, 2010
Chethan Kumar Bangalore, Sept 8, DHNS

Plan not yet finalised for Plaza station on M G Road; Track laying completed only on 3.1 km stretch

The mock coach is all that Bangaloreans will have this New Year, as the work at the Reach-1 of Namma Metro from Byappanahalli to Chinnaswamy Stadium is likely to be delayed.

Going by the progress of work, experts believe that the Bangalore Metro Rail Corporation Limited (BMRCL) will only be able to commission the Reach-1 of the project on the East-West Corridor (6.7 km) by early next year. The big show-stopper for BMRCL is the second station on MG Road that is to come up where the iconic Plaza theatre once stood.
While this is still on the Corporation’s drawing boards, with just about 120 days left for the proposed commissioning, there are ample reasons to believe that the project may miss the deadline.

However, exuding confidence that the project will meet the deadline is BMRCL General Manager (Finance) U A Vasanth Rao.

Speaking to Deccan Herald he said: “I agree nothing has been finalised on the design of the second station on M G Road. However, we are confident that the project will be commissioned in time.”

M N Sreehari, advisor to the State government on infrastructure, traffic and transport, too believes that BMRCL could miss the deadline. “Building such a structure and equipping it with all the amenities required in a full-fledged station would take more than just three months,” he adds.

Should not be a problem

Though Vasanth Rao agreed that the actual structure of the second station may take even an year to complete, he opined that it will not affect the operation of Reach-1. “We’ll have the other station operating in full and are confident of completing the basic structure including the passage connecting the second station for operational purpose. Hence, there should be no problem in meeting the deadline.”

Chairman of the Quality Control Task Force set up by the State government, C S Vishwanath said whether the structure could be completed in three months or not would depend on its composition.

“If steel columns are used, the time required for construction can be considerably reduced, but if they want concrete columns, the duration will be longer,” he said.When asked about the composition of the structure Vasanth Rao said: “The design is yet to be finalised.”

Track laying

Besides, the BMRCL also has other issues like track laying, installation of signalling equipment and also completion of the other stations. While about 62 per cent of the work on the stations is complete, the Corporation is confident of finishing the rest in time. So far, only about 3.1 km of the tracks have been laid on the 6.7 km stretch. The Corporation still has to lay about 10.3 km of rails on the stretch (double track).

The signalling work is also yet to commence as the equipment has not reached India. While experts believe that the installation of a full-fledged automated signalling system could take anywhere between three to four months, BMRCL which seems to be running out of time, seems confident.

Signalling equipment is being imported from France and Portugal, Vasanth Rao said, adding it is expected to arrive in a month’s time.


Go to Top

Photo Gallery
Prime Minister Narendra Modi during BJP's National Council Meeting at Kozhikode...

Prime Minister Narendra Modi during BJP's National Council Meeting at Kozhikode...

Cyclists take part Cyclothon 2016 held on world car free day in Gurgaon...

Cyclists take part Cyclothon 2016 held on world car free day in Gurgaon...

Artists practice Garba in Ahmedabad...

Artists practice Garba in Ahmedabad...

School students at 'Mother Walk' rally to commemorate the canonization of Mother Teresa in Kolkata

School students at 'Mother Walk' rally to commemorate the canonization of Mother Teresa in Kolkata

Maratha community members hold a protest rally demanding justice for Kopardi rape victim...

Maratha community members hold a protest rally demanding justice for Kopardi rape victim...

An aerial view of the flood hit Edupalaya village in Medak district of Telangana...

An aerial view of the flood hit Edupalaya village in Medak district of Telangana...

Indian and U.S. army soldiers take part in an Indo-US army joint combat exercise in Ranikhet...

Indian and U.S. army soldiers take part in an Indo-US army joint combat exercise in Ranikhet...

St Patrick Church celebrating 175th anniversary in Museum Road, Bengaluru...

St Patrick Church celebrating 175th anniversary in Museum Road, Bengaluru...

Army personnel arrive to help flood affected people in Hyderabad...

Army personnel arrive to help flood affected people in Hyderabad...

Prime Minister Narendra Modi with BJP President Amit Shah wave to the crowd at public rally...

Prime Minister Narendra Modi with BJP President Amit Shah wave to the crowd at public rally...

Copyright 2014, The Printers (Mysore) Private Ltd., 75, M.G Road, Post Box 5331, Bengaluru - 560001
Tel: +91 (80) 25880000 Fax No. +91 (80) 25880523