Traffic on Kadur-Arasikere double line commences
DHNS
Last Updated IST

The traffic on Kadur-Arasikere railway doubleline was commissioned, on Wednesday.
Railway work Chief Engineer P D Sharma welcomed Bangalore-Hubli intercity, at Birur.

He said that Arasikere-Birur doubleline work was completed in three years. The line is 44 km. With the double line, the delay in trains due to crossing will be solved. The double line will be completed till Ajjampura, by January end. Executive engineer Padmanabhan, DEE R K Singh, AEE Vinod Kumar and others were present.

Deccan Herald is on WhatsApp Channels| Join now for Breaking News & Editor's Picks

ADVERTISEMENT
ADVERTISEMENT
Read more
(Published 08 November 2012, 01:37 IST)