Ejipura flyover.
Credit: DH File Photo
Many of Bengaluru's infrastructural projects continue to be put on hold, adding to locals' woes. Daily commute proves to be a hassle, as the construction adds to the city traffic and dampens down hopes.
As a few eagerly awaited projects continue to see delays, pushing back initial deadlines, reservations regarding the feasibility grow among experts and citizens.
An integrated flyover at Yelahanka police station circle, Shesharipuram College, and BWSSB Junction is yet to be completed. The construction began in December 2021, and is expected to be finished in January 2026.
Start Date: Dec 2021
Expected completion date: June 2026
The foundational work for set of grade separators to Kengeri outer ring road across Ullal main road, which began November 2020, is expected to be completed by February 2026.
Start Date: Nov 2020
Expected completion date: Feb 2026
A grade separator at HMT Road and Pipeline Road Junction has been in the works from November 2020, and is slated for completion also in February 2026.
Start Date: Nov 2020
Expected completion date: Feb 2026
A grade separator at Outer Ring Road at Kerekodi Road Hosakerehalli Junction is another work underway that began in August 2020. Under construction for over five years, it is projected to be ready by January 2026.
Start Date: Aug 2020
Expected completion date: Jan 2026
DH Graphic
Grade separators to Kengeri Outer Ring Road across Annapoorneshwari Nagara Main Road's completion is targetted to be concluded in March 2026, an endevaour that began in July 2022.
Start Date: July 2022
Expected completion date: Mar 2026
A Pipeline Road via Kurubarahalli, from West of Chord Road to Outer Ring Road, is set to be finished in February 2026, a project that began in July 2022.
Start Date: July 2022
Expected completion date: Feb 2026
A construction work that began in November 2023 persists to frustrate locals, the corridor that connects Ejipura main Inner Ring Road, Sony World Junction, and Kendriya Sadan Junction is said to be completed by June 2026.
Start Date: Nov 2023
Expected completion date: June 2026
A series of improvement works and bridges are ongoing projects that commenced in July 2022, on Ring Road from NH Tumakuru Road Junction to Nayandanahalli Junction, and ORR from Sumanahalli Junction to Ambedkar College, with the anticipated wrap-up being February 2026.
Start Date: July 2022
Expected completion date: Feb 2026
A railway overbridge project that began in March 2024, between the Yelahanka and Channasandra stations, is expected to be completed by February 2026.
Start Date: March 2024
Expected completion date: Feb 2026
Approach ramps to a railway underpass, that connects Yelahanka New town and Old Town near the Yelahanka Railway Station began work in February 2023. As a well-awaited project, it is anticipated to be completed by March 2026.
Start Date: Feb 2023
Expected completion date: March 2026
A bridge over a existing storm water drain, from Halagevaderahalli (near Gopalan Arcade) to Mysuru Road (near Bengaluru University junction) noted a suspended project, a project that was initiated in July 2022.
Along the Subratho Mukherjee road and Peenya Industrial Ring Road, a grade separator project is yet to begin. It was reported that the start date of the project dates back to July 2019 but the actual work is yet to begin.