<p>India’s biggest indigenous <span>nuclear</span> power reactor on Wednesday became operational as criticality was achieved at the country’s first 700-MW power plant at Kakrapar atomic power station in Gujarat.</p>.<p>With the criticality—initiation of the self-sustaining <span>nuclear</span> chain reaction inside the reactor’s core—achieved successfully, the N-power company will conduct few other tests and progressively increase the plant’s output, before it is connected to the grid within a week.</p>.<p>It took 10 long years for the <span>Nuclear</span> Power Corporation of India Ltd to complete the project whose construction began in November 2010.</p>.<p>Read: <a href="https://www.deccanherald.com/national/national-politics/kakrapar-unit-3-to-be-commissioned-in-april-790297.html" target="_blank"><strong>Kakrapar unit 3 to be commissioned in April</strong></a></p>.<p>"Big Day in India's Nuclear history as indigenously designed 700 MWe Kakrapar Atomic Power Plant-3 in Gujarat achieved criticality. Nation salutes our scientists on this stellar achievement. New India is marching ahead to realise PM @NarendraModi's vision of #AatmaNirbharBharat," Amit Shah tweeted.</p>.<p>Prime Minister Narendra Modi too congratulated nuclear scientists, saying the indigenous reactor is a shining example of the 'Make in India' campaign.</p>.<p>The fuel loading of the reactor was completed by the middle of March 2020 following which several tests and procedures were carried out during the lockdown period following all Covid-19 guidelines, NPCIL said in a statement.</p>.<p>Barring two 540 MW units at Tarapur, majority of the Indian <span>nuclear</span> power reactors are pressurised heavy water reactors of 220 MW capacity. In addition, there are two 1000 MW Russian light-water units at Kudankulam, two old 160 MW boiling water reactors at Tarapur and a 200-MW unit at Rawtbhatta.</p>.<p>NPCIL officials blamed the delay in the supply of critical equipment as the main reason for the third unit at the Kakrapar Atomic Power Project to take such a long time. The inner containment dome of KAPP-3 was installed only in June 2016.</p>.<p>Construction of a second 700-MW unit at Kakrapar began in 2011 and is likely to be finished next year.</p>
<p>India’s biggest indigenous <span>nuclear</span> power reactor on Wednesday became operational as criticality was achieved at the country’s first 700-MW power plant at Kakrapar atomic power station in Gujarat.</p>.<p>With the criticality—initiation of the self-sustaining <span>nuclear</span> chain reaction inside the reactor’s core—achieved successfully, the N-power company will conduct few other tests and progressively increase the plant’s output, before it is connected to the grid within a week.</p>.<p>It took 10 long years for the <span>Nuclear</span> Power Corporation of India Ltd to complete the project whose construction began in November 2010.</p>.<p>Read: <a href="https://www.deccanherald.com/national/national-politics/kakrapar-unit-3-to-be-commissioned-in-april-790297.html" target="_blank"><strong>Kakrapar unit 3 to be commissioned in April</strong></a></p>.<p>"Big Day in India's Nuclear history as indigenously designed 700 MWe Kakrapar Atomic Power Plant-3 in Gujarat achieved criticality. Nation salutes our scientists on this stellar achievement. New India is marching ahead to realise PM @NarendraModi's vision of #AatmaNirbharBharat," Amit Shah tweeted.</p>.<p>Prime Minister Narendra Modi too congratulated nuclear scientists, saying the indigenous reactor is a shining example of the 'Make in India' campaign.</p>.<p>The fuel loading of the reactor was completed by the middle of March 2020 following which several tests and procedures were carried out during the lockdown period following all Covid-19 guidelines, NPCIL said in a statement.</p>.<p>Barring two 540 MW units at Tarapur, majority of the Indian <span>nuclear</span> power reactors are pressurised heavy water reactors of 220 MW capacity. In addition, there are two 1000 MW Russian light-water units at Kudankulam, two old 160 MW boiling water reactors at Tarapur and a 200-MW unit at Rawtbhatta.</p>.<p>NPCIL officials blamed the delay in the supply of critical equipment as the main reason for the third unit at the Kakrapar Atomic Power Project to take such a long time. The inner containment dome of KAPP-3 was installed only in June 2016.</p>.<p>Construction of a second 700-MW unit at Kakrapar began in 2011 and is likely to be finished next year.</p>