Oscillation tests to be over by June 23

Oscillation tests to be over by June 23

The instrumentation of Metro coaches was completed on June 9 following which the Railway Design and Standards Organisation (RDSO) conducted trials to test the instrumentation.

The RDSO will issue a speed certificate to the Bangalore Metro Rail Corporation Limited after the conclusion of the oscillation tests. The Corporation subsequently, will approach the Commissioner for Rail Safety (CRS).

Safety inspection

The commissioner in turn will have to conduct a safety inspection before declaring the project “safe” for public, BMRCL sources said.

Commissioner for Rail Safety D K Singh had said that his inspection will not take too long unless there were not too many problems.