Consultants under lens in Karnataka amid project cost overruns
According to draft guidelines, which DH has seen, if the revised estimate of a work exceeds the original cost projection by more than 10 per cent due to shoddy consultancy, a penalty of 10 per cent of the excess amount should be imposed on the consulting firm or consultant responsible for preparing the project plan.